Languages | Sitemap | Become a Dealer

AUTOMATION INSTALLATION SYSTEM PREREQUISITES

 

 

In order to Install S-BUS the following Prerequisites must be available prior to Commencing with Smart-BUS Final Installation and Commissioning:

1. LC Cabling for control System is done as per Schematics and riser diagram examples and is certified
2. Third party systems Installed, coordinated, tested and commissioned and certified like:

a. Lighting fixtures
b. HVAC
c. Gates and Garages
d. Motorized Curtains..etc.

3. Temporary or Permanent Electricity is Connected to all DB's and Panels
4. Space is allocated for Smart-BUS Systems additions Ready with Permanent Power Outlets and connection p to S-BUS cabinets / DB's
5. Final Paint Coat is not yet applied
6. No Wall Paper is applied Yet
7. All Ceiling Access Panels are ready as Needed

Download File: